Tendon manager and construction stage

Good evening,
how to enter the phase number for laying cables as well as the phase number for injection?
And also how to do the construction stage?

In the Tendon Manager and also in all the dialogs for tendon elements in SOFiPLUS you can define construction stages for three states:

Installation
Grouting
Removal

For further processing you can use the CSM program. A example can be found here:

https://docs.sofistik.com/2025/en/tutorials/bridge-design/beam-bridge/beam-bridge.html