For precast pre-tensioned girders please see the following example.
TEDDY > File > Examples… > csm > english > more > csm3_casting_bed_method.dat.
Here it is important to define a special prestressing system without friction and slip.
In order to consider the immediate bond, you have to select the same construction stage for ICS1 and ICS2 in the CS command.
Best regards
Frederik Höller
Your SOFiSTiK Support Team